Latest News

UK energy regulator to reject penalty exemptions for National Grid and SP Energy joint venture

Ofgem, the British energy regulator, said that it did not think an electricity transmission project by National Grid Electricity Transmission & SP Energy Networks qualified to be exempted from penalties related delays.

A joint venture between National Grid units and Iberdrola, a Spanish company, had asked for a 480 day exemption from penalties in relation to delays in the completion of the Eastern Green Link 1 due to global supply-chain issues and capacity shortages.

The project includes subsea cables and underground cables that link Scotland with north-east England. It is an important part of Britain’s goal to decarbonise the electricity sector by 2030.

Ofgem, however, said that it would consider denying the request because supply issues were not present at the time the EGL1 bid was made and the companies had taken measures to reduce the impact of these constraints.

Ofgem approved a funding package of 2 billion pounds ($2.57billion) for the project back in November.

The regulator stated that construction of EGL1 started in March, and now expects it to be completed in April 2029. This is 16 months behind schedule, which will result in penalties of four months for Output Delivery Incentive.

Financial incentives are used to promote timely and efficient delivery of projects. If projects are not delivered on time, a fine of up to 10 percent of the total project cost can be imposed.

The joint venture will be exempted from penalties for delays if approved until April 25, 2020. Currently, it is exempted until December 31, 2020.

EGL1 will be providing further evidence during Ofgem’s consultation period on supply chain issues, including the impact of delivery times. Raechel Thankam Job in Bengaluru and Shashwat awasthi, editing by Janane Venkatraman, Saad sayeed.

(source: Reuters)