The Polish chemicals group Grupa Azoty announced on Tuesday that it had informed prosecutors of alleged safety violations during the launch in 2023 of its flagship Polimery Police Project.

State-controlled chemicals manufacturer said in a press release that the Polimery Police Plant, operated by an Azoty Unit, was built without the necessary permits and under conditions that could have put employees and residents at risk.

The documentation cited by the company alleged that there were a number of defects, and that permits had only been issued in 2024 - months after the plant’s?ceremonial opening.

Malgorzata Crolak, Deputy CEO, said: "Our opinion is that an irresponsible test was conducted, in which?the lives and health?of residents and employees... were at risk."

The project was plagued with cost overruns, delays and other issues.

This was just one of many investigations that the new management at Poland’s state-controlled companies launched into their predecessors’ activities. Azoty had notified the prosecutors of alleged damages related to gas procurement contracts in February.

Today, we are not judging the responsibility of any particular individual. Krolak stated that the assessment was up to prosecutor's offices.

Azoty is facing financial difficulties since?late 2022 due to high gas prices and competition from cheaper imports. In November 2025, it filed its first notification regarding the history of the investment.

In April, the state-owned refiner Orlen signed a preliminary agreement to take over this project.