Capital Power: Meta data center makes Alberta attractive to hyperscalers

Capital Power CEO said that Meta's plan to construct a 'C$13 billion data center' in Alberta, Canada, has increased the appeal of the province for hyperscalers, who view it as a vote 'of confidence' in the government AI strategy.

Avik Dey said that Capital Power has been in contact with a number of potential project proponents about supplying electricity.

He refused to name companies but said that he did not believe Meta would be the only US Hyperscaler to build? a large-scale datacenter in Alberta. Hyperscalers operate large-scale data centers and cloud computing infrastructure to support AI.

Canada only has a few hyperscale data centres operating. Companies have proposed building more than 100 data centers in Alberta. The province has cheap, abundant natural gas for electricity generation, a large amount of land, and a climate that is conducive to supercomputers.

Dey stated that "multiple hyperscalers" have been evaluating Alberta for the past 18 months. "I feel that we have the potential to become a multi-gigawatt marketplace."

Capital Power pitches?its Genesee Generating Station, southwest of Edmonton, as a possible site for large data centres and believes that its natural gas-fired power generating stations are well-suited to service data centers in Canada or the US.

BCE QUADRUPLES THE SIZE OF A SASKATCHEWAN RESOURCE

BCE, a Canadian telecom company, announced last week that it would quadruple its data center plans in Saskatchewan. The new facility will be a 1.2 gigawatt hub. Saskatchewan's government has said that it gives priority to Canadian ownership in assessing any new data center projects.

Alberta is pursuing hyperscalers based in Silicon Valley and giving new proponents an option to build their electricity sources themselves to maximize their capacity.

Meta partnered with Pembina Pipeline to build a natural gas-fired ?electricity-generating station to power its first Canadian data center. Capital Power will provide 250 megawatts of electricity until the project is completed in 2030.

A data center project was promoted at an investment summit last week hosted by Prime Minster Mark Carney. An OpenAI executive also attended.

Data centers in the US are being criticized by communities and legislators for their power, water, and pollution issues. Dey?said Alberta took a measured approach, encouraging data centers to invest in new energy supply instead of relying upon the grid.

A report by the clean energy think-tank 'Pembina Institute' released a month ago said that allowing data centres to draw power from a provincial grid before they have their own generation capacity running would strain the supply and increase electricity costs for consumers.

A July Angus Reid survey found that 68% of Canadians were against a large datacenter near their homes.

(source: Reuters)