Latest News

Three hydroelectric dams in Ecuador offline till water levels recuperate

Three hydroelectric dams in Ecuador have actually stopped running due to low water levels amid the country's worst dry spell in over 60 years, Energy Minister Antonio Goncalves said on Tuesday.

The dams, which assist make up the Paute Integral, consist of the significant Mazar power plant and its tank, which feeds the Molina and Sopladora plants further down river.

The method now is to save Mazar for as long as possible to purchase us time so that everything starts arriving, he informed Reuters after a press conference, describing generators and other steps.

On Monday, authorities stated power cuts across the country would run for approximately 12 hours a day. Goncalves had stated the dry season in Ecuador - which is greatly based on hydropower - had actually started two months early.

The cuts throughout the country are anticipated to continue through Sunday.

The scenario at Mazar is at a vital point, Goncalves said, adding that current steps have assisted water levels in the tank recover by 1.40 square meters.

We were approaching the turning point where we were losing control, Goncalves said.

(source: Reuters)