Poland's very first nuclear reactor approximated to cost over $37 bln

Poland's very first nuclear power plant will cost an approximated 150 billion zloty ($ 37.22 billion),. according to the top energy security official priced estimate by the. staterun news firm PAP.

Poland's previous government chose Westinghouse Electric to. develop the plant on the Baltic coast, however has actually not picked the. monetary design to build it.

The last cost estimate will be possible when the information of. the building contract are offered next year and financing. for the job is closed, Maciej Bando, deputy environment minister. in charge of strategic energy infrastructure was quoted by PAP. as stating on Thursday.

In 2022, the government projected the cost of the plant at. 100 billion zloty and imagined the start of the very first reactor. in 2033. The task suffered delays and is now seen completely. operation by 2040.

We estimate that the building costs of this investment. will be roughly 115 billion zloty, for innovation and. construction works, and approximately 35 billion in costs. including business activities, accompanying financial investments and the. needed reserve, Bando stated.

He said that the crucial date for the job was 2028, when. the concrete foundation for the reactor is set to be poured.

We have statements from the specialist that they require. seven years from this date to complete the process of building. the first reactor, which suggests 2035. The subsequent reactors. will be finished at one-year intervals, Bando stated.

(source: Reuters)