After a rise in the water level on the Danube River, which cools the plant, Hungary began to turn back on a generator at the Paks nuclear power plant on Monday. This will provide some relief for the facility that supplies nearly half of the country's electricty.

In recent weeks, the Danube reached record lows amid a heatwave and a drought that lasted across most of Europe. The plant was forced to run at just 10% of its full capacity. Only one of eight turbines remained operational.

The droughts in Europe this summer have already caused havoc with the power, shipping, and health systems. The economic impact on the region is estimated at hundreds of billions.

In 'Romania, for example, similar problems forced the declaration of an energy emergency for the entire month of August. The flow of the Danube was redirected so that its single nuclear plant could continue to 'operate for the next couple of days.

DANUBE RISE MIGHT BE ONLY TEMPORARY

Peter Magyar, the Hungarian prime minister, said that on Monday work had begun to restart a second Paks turbine after the Danube climbed 19 centimetres over its low of last week.

He said that the second turbine would start producing electricity by Monday evening.

Magyar warned last week that rain in Austria might raise the Danube level, but that it would only be temporary.

Magyar said that last week, the government was working on a longer-term solution. This included reviewing the Paks 2 expansion as the current design makes the new?plant dependent upon cooling water from Danube.

Magyar, who spoke last week, said that it was important to keep the nuclear power plant running, because "the Hungarian economic system cannot function without the plant for months."

Magyar said that the government would also tender 700 megawatts by August 31, and develop four gigawatts by 2030. (Reporting and editing by David Holmes; Anita Komuves and Krisztina than)