Capstone: Grid bottlenecks force businesses to upgrade their onsite power systems

Capstone: Grid bottlenecks force businesses to upgrade their onsite power systems
Capstone: Grid bottlenecks force businesses to upgrade their onsite power systems

Vince Canino, Capstone Energy+ CEO, said that the demand for more onsite power is increasing as businesses struggle to secure enough capacity from their strained American utilities.

Businesses are looking at onsite generation to reduce energy costs, but also as a solution for expanding their business.

Capstone, a provider of microturbines and power systems behind the meter for industrial and commercial customers, has seen a rise in demand from sectors such as?healthcare, and is now pursuing projects involving data centers.

Canino said, "Today’s discussions are about energy security."

Canino said that Capstone customers are now buying larger blocks of energy, such as 3, 4, and 6-megawatt systems, in comparison to smaller projects which were more common?in years past.

A 1 megawatt system can supply electricity to approximately 750-1,000 households at any given time. This depends on the average household demand, as well as location.

As a result, customers are now moving more quickly to obtain onsite power.

"I believe today, many of these cycles are shrinking, because it is no longer about if this investment was a good one and what the return would be. It's not so much about if I want power, but if I can get it when I need it," Canino said.

Capstone installed a combined heat and power 2 MW system at Scripps Mercy Hospital, San Diego. This system provides electricity and backup power during power outages.

Canino stated that the?company? has deployed their technology?at small-scale enterprise data centers, but they have not yet done so at a large data center. Reporting by Arunima in Bengaluru, editing by Devika Syamnath

(source: Reuters)